Effect of Project Planning on Project Performance, A Case of Partnership for Resilient and Inclusive Small Livestock Markets Project in Rulindo District, Rwanda

https://doi.org/10.51867/ajernet.6.1.63

Authors

Keywords:

Communication Planning, Project Planning Practices, Project Performance, Risk Planning, Stakeholder Planning

Abstract

The research sought to investigate the effect of project planning on project performance in Rwanda, focusing on the case of The Partnership for Resilient and Inclusive Small Livestock Market (PRISM) project in Rulindo District. It examined the effect of project communication planning, stakeholder planning, and risk planning on the performance of PRISM  project in this district. The study was guded by stakeholder theory, Organizational information theory, and the theory of constraints. The study employed descriptive and correlational research designs. The target population under this study was 754 and the sample size was 87 respondents. This study employed universal and purposive sampling methods. Purposive sampling also referred to as judgmental or selective sampling, involves the researcher choosing specific individuals from the population based on their judgment. The study used questionnaires and interview and observation guides as research instruments. Descriptive and inferential statistics such as correlation and multiple regression were used to analyze quantitative data after running the collected data through SPSS. In contrast, content analysis was used to analyze qualitative data. Regarding specific objective one, the results revealed that project communication planning has positive and significant effect PRISM project in Rulindo District as indicated by β1 =0.162, p-value = 0.021<0.05, t = 2.347 which means that an increase of one unity in project communication planning would lead to an increase in performance of PRISM project in Rulindo District by 0.162 units. Regarding the second specific objective, the findings showed that project stakeholder planning has positive and significant effect on the performance of PRISM project in Rulindo District as indicated by β2= 0.295, p-value= 0.000<0.05, t= 3.881 which implies that an increase of one unity in project stakeholder planning would lead to an increase in performance of PRISM project in Rulindo District by 0.295 units. With the third specific objective, the results showed that project risk planning has positive effect but is not statistically significant on the performance of PRISM project in Rulindo District as indicated by β3=0.032, p-value=0.616, t=0.507, the implication is that an increase of one unity in project risk planning would lead to an increase in performance of PRISM project in Rulindo district by 0.032 units. The study concludes that communication planning, stakeholder planning and risk planning significantly contribute to predicting and positively influencing the performance of PRISM Project in Rulindo District. Based on the study's results, it was recommended that PRISM projects foster a culture of active communication and collaboration. This can ensure more inclusive and informed decision-making processes by encouraging open channels for employees, and stakeholders to share ideas, insights, and feedback freely. This participatory also  approach fosters engagement, enables balanced decision-making, and cultivates a collaborative environment that drives better problem-solving, innovation, and overall organizational performance.

Dimensions

Aduma, L. K., & Kimutai, G. (2018). Project Risk Management Strategies and Project Performance at the National Hospital Insurance Fund in Kenya. International Academic Journal of Information Sciences and Project Management, 3(2), 80-110.

Alamgir, A., Javed, M. A., Ali, M., Talpur, M. H. A., & Alamgir, A. (2015). Organizational Information Theory (OIT): A mechanism to ensure community participation-A case study of a Malaysian NGO. NICE Research Journal, 8(1), 1-15.

Alpha, K., Onsoti, N., & Kituyi, A. (2021). Project Planning and Implementation in Rwanda National Union of Deaf Project Kicukiro District. Journal of Advance Research in Business Management and Accounting 7(4), 01-16. DOI: https://doi.org/10.53555/nnbma.v7i4.976

https://doi.org/10.53555/nnbma.v7i4.976

Aminah, S. (2016). The Application of Participatory Communication in the Implementation of Small Farmers Empowerment Program. Jurnal Bina Praja, 08(01), 135-148. DOI: https://doi.org/10.21787/JBP.08.2016.135-148

https://doi.org/10.21787/JBP.08.2016.135-148

Angelique, A. (2019). The role of project planning on the performance of government project in Rwanda. Case study: Gishoma power plant project. Jurnal Sains dan Seni ITS, 53(1), 1689-1699.

Asare B, A. (2017). Project Management for Developing Countries: Back to Basics. Dama International Journal of Researchers (DIJR), 2(4), 05-09.

Bloomfield, J., & Fisher, M. J. (2019). Quantitative research design. Journal of the Australasian Rehabilitation Nurses Association, 22(2), 27-30. https://doi.org/10.33235/jarna.22.2.27-30 DOI: https://doi.org/10.33235/jarna.22.2.27-30

Bojnord, N. H., & Afrazeh, A. (2006). Knowledge management in project phases. Journal of Knowledge Management, 13(4), 148-160. https://doi.org/10.1108/13673270910971897 DOI: https://doi.org/10.1108/13673270910971897

Bourne, L., & Walker, D. H. T. (2005). Visualizing and mapping stakeholder influence. Management Decision, 43(5), 649-660. DOI: https://doi.org/10.1108/00251740510597680

https://doi.org/10.1108/00251740510597680

Diallo, A., & Thuillier, D. (2005). The success of international development projects, trust and communication: An African perspective. International Journal of Project Management, 23(3), 237-252. https://doi.org/10.1016/j.ijproman.2004.10.002 DOI: https://doi.org/10.1016/j.ijproman.2004.10.002

El-Saboni, M., Aouad, G., & Sabouni, A. (2009). Electronic communication systems effects on the success of construction projects in United Arab Emirates. Advanced Engineering Informatics, 23(1), 130-138. https://doi.org/10.1016/j.aei.2008.07.005 DOI: https://doi.org/10.1016/j.aei.2008.07.005

El-Sawalhi, N. I., & Hammad, S. (2015). Factors affecting stakeholder management in construction projects in the Gaza Strip. International Journal of Construction Management, 15(2), 157-169. https://doi.org/10.1080/15623599.2015.1035626 DOI: https://doi.org/10.1080/15623599.2015.1035626

Ephantus, E., Wanderi, N., Mberia, H., & Oduor, J. (2015). Evaluation of factors influencing total quality management implementation in Rwadan construction companies: case of fair construction company. Eur J Bus Soc Sci, 4(03), 14-28.

Eric, M., Jean de dieu, D., Placide, M., & Gemariel, N. (2020). Effect of Project Planning Practices on Improving Project Performance in Rwanda. A Case of Huguka Dukore Akazi Kanoze Project in Nyabihu District (2017-2020). International Journal of Social Sciences: Current and Future Research Trends (IJSSCFRT) ISSN, 13(1), 88-94.

Fine, B. (2008). Social capital versus social history. Social History, 33(4), 442-467. https://doi.org/10.1080/03071020802410445 DOI: https://doi.org/10.1080/03071020802410445

Freeman, R. E., & McVea, J. (2005). A stakeholder approach to strategic management. The Blackwell handbook of strategic management, 12(1), 183-201. https://doi.org/10.1111/b.9780631218616.2006.00007.x DOI: https://doi.org/10.1111/b.9780631218616.2006.00007.x

Gichimu, E. M., & Mutuku, M. (2022). Stakeholder management and performance of county government funded projects in Nyeri County, Kenya. The Strategic Journal of Business & Change Management, 9(4), 761-774. https://doi.org/10.61426/sjbcm.v9i4.2449 DOI: https://doi.org/10.61426/sjbcm.v9i4.2449

Goldratt, E. M. (1990). What is this thing called Theory of Constraints and how should it be implemented? North River Press.

IFAD. (2019). Rwanda Project for Inclusive Small Livestock Markets (PRISM) Project Design Report. International Fund for Agricultural Development.

IPAR. (2018). Rwanda Agriculture Finance year book: Public Financing in Rwanda's Agriculture Sector. Institute of Policy Analysis and Research.

Irfan, M., Khan, S. Z., Hassan, N., Hassan, M., Habib, M., Khan, S., & Khan, H. H. (2021). Role of project planning and project manager competencies on public sector project success. Sustainability (Switzerland), 13(3), 1-19. https://doi.org/10.3390/su13031421 DOI: https://doi.org/10.3390/su13031421

Kabir, S. M. S. (2016). Methods of data collection. Basic guidelines for research: An introductory approach for all disciplines, 1(9), 201-275.

Kallio, H., Pietilä, A. M., Johnson, M., & Kangasniemi, M. (2016). Systematic methodological review: developing a framework for a qualitative semi‐structured interview guide. Journal of advanced nursing, 72(12), 2954-2965. https://doi.org/10.1111/jan.13031 DOI: https://doi.org/10.1111/jan.13031

Kohli, A. S., & Gupta, M. (2010). Improving Operations Strategy: Application Of TOC Principles In A Small Business.Journal of Business & Economics Research (JBER), 8(4), 1942-2512. DOI: https://doi.org/10.19030/jber.v8i4.713

https://doi.org/10.19030/jber.v8i4.713

Mabin, V. (1990). Goldratt's "Theory of Constraints" thinking processes: A systems methodology linking soft with hard. History, 20 (2), 1-12.

MINAGRI. (2020). Minagri Annual Report 2019-2020. Ministry of Agriculture and Animal Resources, Rwanda.

Missonier, S., & Loufrani-Fedida, S. (2014). Stakeholder analysis and engagement in projects: From stakeholder relational perspective to stakeholder relational ontology. International journal of project management, 32(7), 1108-1122. DOI: https://doi.org/10.1016/j.ijproman.2014.02.010

https://doi.org/10.1016/j.ijproman.2014.02.010

Monday, T. U. (2020). Impacts of interview as research instrument of data collection in social sciences. Journal of Digital Art & Humanities, 1(1), 15-24. https://doi.org/10.33847/2712-8148.1.1_2 DOI: https://doi.org/10.33847/2712-8148.1.1_2

Mohsin, A. U. (2021). Impact of Project Planning on Project Success: Moderating Role of Transformational Leadership & Mediating effect of Risk Management. Master of Sciences). Capital University.

Mugenga, M., & Bugingo, E. (2024). Effect of risk management on the performance of construction projects in Musanze District, Rwanda (Project INES-Busogo, GS Kampanga Road): A case of New Product Developer (NPD Ltd). Brainae Journal, 8(3), 1-15.

Njuguna, P. G. (2019). Risk management practices and performance of projects in Nairobi City County, Kenya. International Academic Journal of Information Sciences and Project Management, 3(2), 111-136.

Numuhire, G. & Kwena, R. (2022) investigated the planning and sustainability of the Rwanda education assistance project in Rwamagana District. Global Scientific Journals, 10(11), 2320-9186.

Nyandongo, K. M., & Davids, M. (2020). The impact of communication on project performance: An empirical study. 26th International Association for Management of Technology Conference, IAMOT 2017, 404-425.

PMI. (2017). PMBOK® Guide Sixth Edition (PMI, 2017). In Project Management Institute (Vol 6).

Rajablu, M., Marthandan, G., & Yusoff, W. F. W. (2014). Managing for stakeholders: The role of stakeholder-based management in project success. Asian Social Science, 11(3), 111-125. DOI: https://doi.org/10.5539/ass.v11n3p111

https://doi.org/10.5539/ass.v11n3p111

Ruzindana, A., & Irechukwu, E. N. (2023). Strategic Management Practices and Sustainability of Small and Medium Sized Enterprises in Processing and Manufacturing Sector in Rwanda: A Case of 7 Selected Small and Medium Sized Enterprises in Rwanda. Journal of Entrepreneurship & Project Management, 7(13), 61-80. DOI: https://doi.org/10.53819/81018102t2249

https://doi.org/10.53819/81018102t2249

Silvius, A. J. G., & Schipper, R. P. J. (2014). Sustainability in project management: A literature review and impact analysis. Social Business, 4(1), 63-96. https://doi.org/10.1362/204440814X13948909253866 DOI: https://doi.org/10.1362/204440814X13948909253866

Şimşit, Z. T., Günay, N. S., & Vayvay, Ö. (2014). Theory of Constraints: A Literature Review. Procedia - Social and Behavioral Sciences, 150(September 2014), 930-936. DOI: https://doi.org/10.1016/j.sbspro.2014.09.104

https://doi.org/10.1016/j.sbspro.2014.09.104

Singirankabo, M., & Wanjiku, C. (2023). Effect of Project Communication Practices on Performance of the International Non-Governmental Organizational Projects in Rwanda. Journal of Entrepreneurship & Project Management, 7(7), 48-59. DOI: https://doi.org/10.53819/81018102t3093

https://doi.org/10.53819/81018102t3093

Takim, R., & Adnan, H. (2008). Analysis of effectiveness measures of construction project success in Malaysia. Asian Social Science, 4(7), 74-91. https://doi.org/10.5539/ass.v4n7p74 DOI: https://doi.org/10.5539/ass.v4n7p74

Tesfaye, E., Lemma, T., Berhan, E., & Beshah, B. (2017). Key project planning processes affecting project success. International Journal for Quality Research, 11(1), 159-172.

Thaddee, B., Prudence, N., & Valens, S. (2020). Influence of project management practices on project success in Rwanda-the case of Girinka project in Runda sector, Kamonyi district, Rwanda. European Journal of Management and Marketing Studies, 5(3), 2501-9988.

Umulisa, C., & de Dieu Dushimimana, J. (2023). Effect of Project Planning Practices on Performance of Improve Capacity for Supply of Quality in Reproductive Health Services Project in Nyamasheke District, Rwanda. Journal of Entrepreneurship & Project Management, 7(15), 163-172. https://doi.org/10.53819/81018102t2294 DOI: https://doi.org/10.53819/81018102t2294

Védaste, M., & Michael, D. S. (2024). Project Management Practices and Performance of Agricultural projects at Rwanda Diary development project, globalscientificjournal 12(1), 2320-9186.

Williams, K., & Munene Muiruri, P. (2022). Influence of Project Planning Process on Performance of Food Sustainable Initiative Project in Rwanda. 10(3), 912-929.

Woldie, D. S. (2016). The role of project planning on project performance in Ethiopia (Master's thesis, Addis Ababa University, Addis Ababa).

Zwikael, O., & Ahn, M. (2011). The effectiveness of risk management: an analysis of project risk planning across industries and countries. Risk Analysis: An International Journal, 31(1), 25-37. https://doi.org/10.1111/j.1539-6924.2010.01470.x DOI: https://doi.org/10.1111/j.1539-6924.2010.01470.x

Published

2025-03-14

How to Cite

Uwera, G., & Dushimimana, J. de D. (2025). Effect of Project Planning on Project Performance, A Case of Partnership for Resilient and Inclusive Small Livestock Markets Project in Rulindo District, Rwanda. African Journal of Empirical Research, 6(1), 736–750. https://doi.org/10.51867/ajernet.6.1.63

Most read articles by the same author(s)

1 2 > >>