Moderating influence of stakeholder participation on the relationship between risk management strategies and implementation of KeRRA road construction projects in Migori County, Kenya
DOI:
https://doi.org/10.51867/ajernet.7.2.12Keywords:
KeRRA, Migori County, Road Construction Projects, Stakeholder Participation, Risk ManagementAbstract
The purpose of this study was to determine the moderating influence of stakeholder participation on the relationship between risk management strategies and implementation of KeRRA road construction projects in Migori County. Guided by stakeholder theory, the study adopted a pragmatic research philosophy, which integrates analytic frameworks of descriptive and inferential statistics. The target population was 419, with a sample of 234, which included 39 contractors, 193 Sub County Roads Committee (SCRC) members, and 2 Kenya Rural Roads Authority (KeRRA) engineers, selected by random and purposive sampling techniques. Data were collected with the help of a questionnaire for contractors and SCRC members and a research schedule for key informant interviews with engineers. Data were analyzed using both descriptive and inferential statistics with the help of the Statistical Package for Social Sciences, SPSS. The study utilized the t-statistic to test the null hypotheses. Validity and reliability of research instruments were ensured through a pilot survey and expert evaluation. The results showed that stakeholder participation has a significant influence on the relationship between risk management strategies and implementation of road construction projects. It has a positive and significant direct impact on road construction projects, with an estimated t-statistic value of |t| = 10.321, against the theoretical t-statistic value of |t05| = 1.943. In general, it is concluded that stakeholder participation significantly moderates the relationship between risk management strategies and implementation of KeRRA road construction projects in Migori County (|t| = 10.321). The study recommends that all categories of stakeholders need to be consulted and considered during the risk management process and implementation of road construction projects. In summary, KeRRA should institutionalize structured stakeholder engagement throughout the project lifecycle. Project managers should therefore integrate stakeholder participation into formal risk management plans rather than treating it as a peripheral activity.
Downloads
References
Abdul-Rahman, H., Takim, R., & Min, W. S. (2021). Financial-related causes contributing to project delays. Journal of Retail and Leisure Property, 8(3), 225-238. https://doi.org/10.1057/rlp.2021.11 DOI: https://doi.org/10.1057/rlp.2009.11
Adhikari, R. (2020). Risk management practices in urban road construction projects in Shiddharthanagar Municipality, Rupandehi, Nepal (Master's thesis, Lumbini Engineering, Management and Science College).
Asiedu, R., & Faisal, I. (2022). Value co-creation approach to management of construction project stakeholders in Ghana. Journal of Construction in Developing Countries, 27(1), 1-23. https://doi.org/10.21315/jcdc2022.27.1.1 DOI: https://doi.org/10.21315/jcdc2022.27.1.1
Baker, S. W. (2021). Risk management in major projects. Ameada Hess Ltd.
Bhasin, H. (2020). What is the stakeholder theory strategy? Marketing91. https://www.marketing91.com/what-is-the-stakeholder-theory
Chohen, H. (2020). Project management statistics: 45 stats you cannot ignore. https://www.workamajig.com/blog/project-management-statistics
Claus, B., Daniel, J., Alexander, K., Siemens, A. G., & Otto, H. R. (2020). Behaviour of internal stakeholders in project portfolio management and its impact on project success. International Journal of Project Management, 10(4), 356-379.
Creswell, J. W. (2023). Research design: Qualitative, quantitative, and mixed methods approaches (3rd ed.). Sage Publications.
Donaldson, T., & Preston, L. (1995). The stakeholder theory of the corporation: Concepts, evidence, and implications. Academy of Management Review, 20(1), 65-91. https://doi.org/10.2307/258887 DOI: https://doi.org/10.2307/258887
Government of Kenya. (2020). County integrated development plan (CIDP) 2018-2022: Migori County. https://migori.go.ke
Government of Kenya. (2023). County integrated development plan 2023-2027: Migori County. https://repository.kippra.or.ke
Gujarati, D. (2020). Basic econometrics (4th ed.). McGraw-Hill.
Hodges, O. (2020). The impact of training implementation designed to target emotional intelligence abilities of project managers. International Journal of Project Management, 28(5), 461-468. https://doi.org/10.1016/j.ijproman.2009.08.004 DOI: https://doi.org/10.1016/j.ijproman.2009.08.004
Kalu, C. M., & Maina, R. (2021). Stakeholder involvement and infrastructure projects implementation at Kenya Ports Authority. International Journal of Business Management, Entrepreneurship and Innovation, 3(1), 78-90. https://doi.org/10.35942/jbmed.v3i1.166 DOI: https://doi.org/10.35942/jbmed.v3i1.166
Kamassi, A., Abd Manaf, N. H., & Omar, A. (2020). The identity and role of stakeholders in the medical tourism industry: State of the art. Tourism Review, 75(3), 559-574. https://doi.org/10.1108/TR-01-2019-0031 DOI: https://doi.org/10.1108/TR-01-2019-0031
Kenya National Bureau of Statistics. (2019). Migori County statistical report. Kenya National Bureau of Statistics/
Klynveld Peat Marwick Goerdeler (KPMG). (2021). KPMG East Africa Kenya workbench report. https://kpmg.com
Lim, R. (2020). 15 fascinating project management statistics. https://hive.com/blog/project-management
Lincoln, Y. S., Lynham, S. A., & Guba, E. G. (2020). Paradigms and perspectives in contention. In N. K. Denzin & Y. S. Lincoln (Eds.), The Sage handbook of qualitative research (pp. 91-95). Sage Publications.
Mugenda, O., & Mugenda, A. (2003). Research methods: Quantitative and qualitative approaches. Acts Press.
Mupende, T. (2023). Analysis of project monitoring practices on implementation of road construction in Rwanda: A case of Sonatube-Bugesera Road. International Journal of Scientific Research and Management, 11(2), EM-2023-4626-4640. https://doi.org/10.18535/ijsrm/v11i02.em11 DOI: https://doi.org/10.18535/ijsrm/v11i02.em11
Muturi, P., & Oguya, S. (2022). Factors affecting road construction projects in arid and semi-arid lands (ASAL) regions of Kenya: A case of Isiolo Sub-County. International Journal of Social Sciences and Technology, 2(8), 908-929.
Njogu, E. M. (2020). Influence of stakeholder involvement on project performance: A case of NEMA automobile emission control project in Nairobi County, Kenya (Master's thesis, University of Nairobi).
Odeck, J. (2021). Cost overruns in road construction: What are their sizes and determinants? Transport Policy, 11(1), 43-53.
https://doi.org/10.1016/S0967-070X(03)00017-9 DOI: https://doi.org/10.1016/S0967-070X(03)00017-9
Opeoluwa, A., Mushatu, W., Nokulunga, M., Aigbavboa, C., & Didibhuku, T. (2022). Learning from existing errors: External stakeholders' impact on road infrastructure projects. Advances in Human Factors in Management and Leadership, 55, 24-31. https://doi.org/10.54941/ahfe1002228 DOI: https://doi.org/10.54941/ahfe1002228
Rajeev, D., & Pradeep, D. (2021). Role of stakeholders in project success: Theoretical background and approach. International Journal of Finance, Insurance and Risk Management, 11(1), 38-49. https://doi.org/10.35808/ijfirm/248 DOI: https://doi.org/10.35808/ijfirm/248
Roya, D., Rodney, T., & Mauro, M. (2022). Project governance and stakeholders: A literature review.
Saunders, M., Lewis, P., & Thornhill, A. (2020). Research methods for business students (6th ed.). Pearson Education Limited.
Segal, T. (2020). Common methods of measurement for investment risk management. https://www.investopedia.com
Shubina, L. Y., Shemyatikhina, M. V., & Evseeva, K. S. (2020). Risk management at implementation of social projects of public-private partnership. Advances in Economics, Business and Management Research, 128(15), 634-927. https://doi.org/10.2991/aebmr.k.200312.328 DOI: https://doi.org/10.2991/aebmr.k.200312.328
Tserng, P., Cheng, C., Chun-Hung, C., & Yu-Fan, L. (2021). Developing a risk management process for infrastructure projects using IDEF0. Sustainability, 13(12), 6958. https://doi.org/10.3390/su13126958 DOI: https://doi.org/10.3390/su13126958
Vukawanadi, F., & Mkandawire, C. (2021). Risk management practices on road maintenance projects in Malawi (2014-2020) (Master's dissertation, University of Bolton).
Wagude, A. (2019). Moderating influence of conflict resolution on the relationship between transformational leadership and implementation of constituency development fund construction projects in public secondary schools in Kisumu County, Kenya. European Scientific Journal, 15(16). https://doi.org/10.19044/esj.2020.v15n16p311 DOI: https://doi.org/10.19044/esj.2019.v15n16p311
Weyama, J. A. (2020). Stakeholder influence in institutional strategic planning practices in public secondary schools in Kenya. International Journal of Economic Behavior and Organization, 6(1), 22-28. https://doi.org/10.11648/j.ijebo.20180601.13 DOI: https://doi.org/10.11648/j.ijebo.20180601.13
World Bank. (2021). Rural development indicators handbook (2nd ed.). World Bank. http://www.worldbank.org
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Lennard William Bundeh

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.